Fareham Shopping Centre's £9.447m refit has gone out to tender, with work due from June 2027 to October 2028. No planning application has appeared yet.

Builders are now due to start on Fareham Shopping Centre’s £9.4 million refit in June 2027, with the main contract to finish by October 2028. That is later than the February 2027 start the council set out in July.

The new dates are in the council’s tender for the work. It was published on Find a Tender on 15 October and gives an estimated contract value of £6.5 million.

Overview

  • What: new entrances, a covered shopping arcade, refitted Thackeray and Westbury squares, new public toilets and maintenance work across the centre.
  • Cost: a capital budget of £9,447,000, approved on 22 July 2026.
  • When: the arcade contract’s intended start is June 2027, finishing no later than October 2028.
  • Still to come: a planning application, which has not yet appeared in the council’s weekly lists.

What the council approved

Fareham Borough Council owns the shopping centre. Its Executive approved the spending at a special meeting on 22 July. The report to that meeting splits the £9,447,000 three ways:

Part of the work Budget
Phase one: entrances, arcade and toilets £5,556,820
Phase two: the retained east and west malls and Delme Square £2,606,120
Maintenance across both phases £1,284,060
Horizontal bar chart of the £9,447,000 budget for Fareham Shopping Centre: phase one entrances, arcade and toilets £5,556,820; phase two east and west malls and Delme Square £2,606,120; maintenance across both phases £1,284,060. Source: Fareham Borough Council report to the Executive, 22 July 2026.
Chart by Fareham News. Source: Fareham Borough Council, report to the Executive, 22 July 2026.
Share this chartFacebookWhatsAppX

The report says £3,655,000 will come from capital receipts expected in 2026/27 and part of the council’s spending reserve. The other £5,792,000 would be borrowed.

The report calls the borrowing for phase one and maintenance affordable. It adds that the £2,606,120 for phase two “might need to be considered against the timing and value of future capital programme priorities”.

The council’s press release on the decision says the designs are by Leslie Jones Architecture. It quotes the council leader, Councillor Simon Martin: “This is an exciting milestone in our plans to regenerate Fareham Town Centre.”

What will change inside the centre

The tender sets out the planned work in more detail than anything the council has published before. It includes:

  • the North, South and East entrances reclad in anodised aluminium and porcelain tiles, with metal arches and new automatic sliding doors
  • the old terrazzo floors in the north and south malls covered with a new resin floor
  • new ceilings, lighting and tiled columns along the malls
  • a hanging light feature of brown and red tubes in Westbury Square, and three pendant lights under the rooflight in Thackeray Square
  • new toilets in existing units, including a Changing Places toilet with a hoist, an accessible toilet and a baby change

The tender says the scope can still change with design work, budget approval and the council’s final requirements.

The arcade is meant to make a covered walking route from Fareham Live and the Civic Gardens through to West Street. The July report says the evening route through the centre stays open until 11.30pm. It also says Fareham Live sold over 170,000 tickets in its first year.

Why part of the centre will go

The refit covers only the parts of the centre the council plans to keep. Its town centre masterplan page lists “demolition of part of Fareham Shopping Centre to ‘right-size’ the retail offer” as one of its guiding principles.

The council’s consultation page for the emerging masterplan proposed demolishing the east side of the centre and the adjoining multi-storey car park. New homes, a new public square and green space would replace them. The July report says the refit is happening “in advance of proposed demolition and redevelopment of the eastern side”.

The planning application

The July report’s timetable put the planning application in September 2026. It has not appeared in any of the council’s weekly planning lists published since late August, up to the week ending 8 November. The masterplan page still says an application “will be submitted later this year”.

The tender closed for expressions of interest on 26 October. The council expects to invite the shortlisted builders to tender on 4 January 2027. It is using a competitive dialogue, a process in which the council talks through its plans with the bidders before they price the work.

What it means for you

The centre will stay open while the work goes on. The tender asks for builders who can work in a “live” shopping centre. It says that work may happen in the evenings, at night and at weekends, with hoardings and phasing to keep routes and fire exits open.

The council has said the library, Citizens Advice, NHS services and the Job Centre will all stay in the town centre under the wider masterplan. Hampshire County Council has backed moving Fareham Library into another unit in the shopping centre, in principle only.

When the planning application is lodged, anyone can comment on it before a decision is made.